solve a and b please Problem #3 (3 pts): Consider two manufacturing processes for production of malleable iron castings, and the mean and standard deviation
solve a and b please
Problem \#3 (3 pts): Consider two manufacturing processes for production of malleable iron castings, and the mean and standard deviation of one dimension of the castings resulting from these two processes are shown in the following table. The specifications on this dimension are given as 1000.10mm. (a) Calculate Cp and Cpk of these two processes (b) Which of the two processes would you prefer to use and whyStep by Step Solution