Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Southern Energy is in the process of deciding whether to build a new gas-fired power plant that would serve specifically a large cluster of manufacturing

image text in transcribed

Southern Energy is in the process of deciding whether to build a new gas-fired power plant that would serve specifically a large cluster of manufacturing businesses in an industrial park near London. To that end, it needs to estimate the likely costs of producing electricity over the next 5 years and the revenues that can be generated by selling the electricity produced to the business in the industrial park. However, since the costs of producing electricity are mostly dependent on the price of gas, the first task is to forecast future gas prices. Additionally, the revenue from selling electricity depends largely on electricity demand, so forecasts of electricity demand are also necessary.

Gas prices (per cubic meter- m3) are thought to depend on two major factors; the prices of alternative fuels (PF, an aggregate index measure of prices of other fuels that can generate electricity, mainly oil and coal) and changes in the general global economic environment, measured as changes in the global Gross Domestic Product (GDP). Data for those two factors together with the observed price of gas over the past 5 years, as well as the demand of the manufacturing businesses in the park is given in table 1.

The first goal of Southern Energy is to create a forecast of gas prices and electricity demand for the next 5 years, under three scenarios; Base, Faster growth and Slower growth:

The Base scenario assumes that the conditions that drive prices for alternative fuels and the trends of electricity demand in the industrial park will persist in the near future. Southern Energy also assumes that global GDP change measure will be 1.5% per quarter. The company estimates that the probability of the Base scenario taking place is 40%.

The Faster growth scenario assumes that global demand will increase at a faster rate, which would result in increases in both the price of alternative fuels and global GDP at a rate higher than the base scenario. However, faster growth would also increase the electricity demand from the industrial park. The company estimates that the probability of the Faster growth scenario taking place is 35%.

The Slower growth scenario assumes that global demand will slow down, which would result in slower increases in prices and demand or even periods of decrease relative to the base scenario.

The forecast values for both the Faster and Slower growth scenarios can be calculated by applying the following percentage changes to demand values and possible explanatory factors of the Base Scenario:

Southern Energys second goal is to estimate the likely profit under these scenarios and use this information in selecting the optimal strategy to adopt for the Year 6 to Year 10 period. To do so, it has to take into account these facts:

One cubic meter (m3) of natural gas produces 11 kW of electricity.

The electricity demand is given in average MW per hour for a given quarter. There are 91 days in a quarter.

The gas-fired power plant can produce electricity as demand dictates (no additional costs for fluctuating demand or running under a certain capacity). It will produce electricity for the industrial park only and its maximum generating capacity is 600 MW/h. The industrial park will absorb all electricity produced as long as there is demand. So for example, if the demand from the industrial park is 500 MW/h in a given quarter, the plant will use just enough gas to generate 500 MW/h and the industrial park will absorb the full 500 MW/h. If Demand is 700 MW/h, the plant will generate up to its capacity, ie 600 MW/h, and the remaining demand will be sourced from the national grid.

The price of electricity has already been negotiated with the industrial park and is set at a constant 0.011 per kW produced.

The initial investment cost for the power plant is 124 million (build cost) and will be fully operational at the start of year 6. It has fixed operating costs of 320,000 per quarter (additional to gas costs required to generate electricity). At the end of year 10, the residual life of the plant will be 103 million.

Given the above information, Southern Energy is considering three possible courses of action:

Build the power plant as detailed above (standard plant), assuming that the investment is profitable.

Build a larger capacity power plant. The larger plant will require an additional investment of 34 million and will incur fixed operating costs of 395,000 per quarter, but will increase maximum generating capacity to 850 MW/h and the residual value to 131 million.

Take on an additional contract to supply electricity to a nearby aluminium refinery at a price of 0.010 per kW sold. The contract stipulates that Southern Energy must supply 75 MW/h to the refinery before supplying anybody else in the industrial park. After taking on the contract, Southern Energy still needs to decide whether to build the standard plant or the larger capacity plant, as detailed above.

In all instances, the cost of capital of Southern Energy is 1.72% per quarter and all monetary values are in current prices (not taking into account the time-value of money).

Additionally, Southern Energy would also like to explore the sensitivity of the initial results to the following changes:

1) The Uplift parameters for the Faster growth scenario become:

Table 1: Historic gas prices, influencing factors and electricity demand Year 1 1 1 1 2 2 2 2 3 3 3 3 4 4 4 4 5 5 5 5 Gas Prices (s per Prices of alternative Electricity demand Quarter 1000's m3) fuels (PF) GDP (MW/h) 1 96.41 81.82 2.38% 458.71 2 116.86 104.85 2.08% 136.82 3 119.47 115.75 1.78% 120.94 4 112.06 114.65 1.58% 155.14 1 46.84 82.54 - 1.30% 549.05 2 78.07 102.87 -2.22% 206.49 3 55.73 98.13 -2.41% 78.37 4 83.97 118.02 -1.30% 314.28 1 113.99 74.88 3.02% 538.83 2. 168.84 92.04 4.75% 323.22 3 126.45 99.57 5.18% 266.30 4 122.76 127.85 3.89% 380.30 1 87.64 92.01 2.49% 608.77 2 140.16 132.28 2.26% 285.47 3 115.45 100.22 2.04% 255.69 4 81.72 103.97 2.26% 543.90 1 88.01 112.39 0.26% 541.11 2 77.13 98.55 0.20% 379.48 3 61.74 84.31 0.18% 405.90 4 82.23 102.05 0.16% 484.25 5% Table 1: Uplift parameters to Base values for the faster and slower growth scenarios Faster Growth Slower Growth Year PF GDP (%) Electricity PF GDP (%) Electricity demand demand 6 5% 2.5 3% 1 -10% 7 10% 3 7% 0% -0.5 -8% 4% 3 10% -5% -5% 3% 2.5 6% -10% 0.5 -3% 10 2% 2 4% -3% 0.7 0% Note: For GDP, replace the base assumption with the one provided in this table. 8 0 9 Year PF Faster Growth GDP Electricity (%) demand 2.5 15% 6 7 7% 12% Table 1: Historic gas prices, influencing factors and electricity demand Year 1 1 1 1 2 2 2 2 3 3 3 3 4 4 4 4 5 5 5 5 Gas Prices (s per Prices of alternative Electricity demand Quarter 1000's m3) fuels (PF) GDP (MW/h) 1 96.41 81.82 2.38% 458.71 2 116.86 104.85 2.08% 136.82 3 119.47 115.75 1.78% 120.94 4 112.06 114.65 1.58% 155.14 1 46.84 82.54 - 1.30% 549.05 2 78.07 102.87 -2.22% 206.49 3 55.73 98.13 -2.41% 78.37 4 83.97 118.02 -1.30% 314.28 1 113.99 74.88 3.02% 538.83 2. 168.84 92.04 4.75% 323.22 3 126.45 99.57 5.18% 266.30 4 122.76 127.85 3.89% 380.30 1 87.64 92.01 2.49% 608.77 2 140.16 132.28 2.26% 285.47 3 115.45 100.22 2.04% 255.69 4 81.72 103.97 2.26% 543.90 1 88.01 112.39 0.26% 541.11 2 77.13 98.55 0.20% 379.48 3 61.74 84.31 0.18% 405.90 4 82.23 102.05 0.16% 484.25 5% Table 1: Uplift parameters to Base values for the faster and slower growth scenarios Faster Growth Slower Growth Year PF GDP (%) Electricity PF GDP (%) Electricity demand demand 6 5% 2.5 3% 1 -10% 7 10% 3 7% 0% -0.5 -8% 4% 3 10% -5% -5% 3% 2.5 6% -10% 0.5 -3% 10 2% 2 4% -3% 0.7 0% Note: For GDP, replace the base assumption with the one provided in this table. 8 0 9 Year PF Faster Growth GDP Electricity (%) demand 2.5 15% 6 7 7% 12%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Core Concepts Of Accounting Information Systems

Authors: Nancy A. Bagranoff, Mark G. Simkin, Carolyn Strand Norman

11th Edition

9780470507025, 0470507020

More Books

Students also viewed these Accounting questions