Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Southfork Development Co. Southfork plans to develop, and then own and operate, Rolling Meadows for a long period of time. Rolling Meadows Center is a

Southfork Development Co. Southfork plans to develop, and then own and operate, Rolling Meadows for a long period of time. Rolling Meadows Center is a high-quality shopping center development located in an upper-income neighborhood.

It plans to use both interim and permanent financing and has approached the Citadel Life Insurance Company to provide permanent financing. If Southfork planned to sell the shopping center after completion and lease-up, it might have elected to pursue a mini-perm loan. In either case, much of the underwriting analysis and contingencies that follow would be applicable.

Table 1 below contains a breakdown of site size, floor-to-area ratio, parking, and anticipated construction and permanent financing. It also provides percentage breakdowns for building coverage, parking, and open space.

The lender will review the percentage breakdowns to ascertain whether the density of the project development on the site is too high and whether parking is adequate. The lender will pay particular attention to the site plan and ease of traffic circulation on the site. Citadel will have access to comparative data for this project from previous project financing files and from industry statistics.

Table 2 below breaks down development costs into land acquisition costs, off-site costs, hard costs, and soft costs. These costs are also broken down as a percentage of total cost and cost per square foot of gross building area (GBA).

Question 11 pts

Construction Loan Request

Now, let's consider a construction loan request.

Table 2 contains a breakdown of the loan request. Note that this particular loan request does not include land cost. Also note that it does not ask for financing for all soft costs.

However, Southfork is requesting funding for some off-site improvements. The total loan request is $9,001,416, which represents about _________ percent of the $11,982,287 estimate of total project cost (land plus all other outlays).

Group of answer choices

75%

65%

55%

85%

Flag question: Question 2Question 21 pts

Can you take a look at the components of total amount? What are included in the loan request?

Group of answer choices

site improvement + hard construction costs+soft costs+ interest carry

site improvement + hard construction costs+soft costs

site improvement + hard construction costs

site improvement+equity requirements

Flag question: Question 3Question 31 pts

Based on the last question, I think you find an interesting thing in construction lending-----interest.

It is very common in construction lending because the project would not generate much rent or cash inflow during development.

Now, let's help the developer figure out a loan repayment schedule. Can you copy and past this table into your excel. Use table 1 and table 2 as your background information. I provide some numbers for month 12 as your reference.

Hint: table 1 shows the construction loan details.

What is the loan payment for the first 4 months?

Group of answer choices

$1,557,938

$1,457,938

$1,357,938

$1,257,938

Flag question: Question 4Question 41 pts

What is the loan payment from month 5 to month 12?

Group of answer choices

$259,656

$269,656

$249,656

$279,656

Flag question: Question 5Question 51 pts

Alright, now, you basically finish the first column (a) project costs. We can figure out the second column. What would be interest for each month?

Hint: Current month's interest would depend on the loan balance by the end of last month. Loan balance would increase each month, and it would be project costs + construction interest.

Based on your excel, what is the construction interest for month 4?

Group of answer choices

47,207

46,207

45,207

44,207

Flag question: Question 6Question 61 pts

What is the total loan balance for month 10?

Group of answer choices

8,312,427

8,412,427

8,512,427

8,612,427

Flag question: Question 7Question 71 pts

Now, can you add up all your interest payment? What is the total interest? Can you double check table 2. What is the total interest carry? Are they the same?

Group of answer choices

$ 692,416

$ 682,416

$ 672,416

$ 662,416

Flag question: Spacer

A couple important notes about interest draw.

You calculated the interest draw. Interest draws are computed on the outstanding monthly loan balance and are borrowed as a part of the construction cost draws at the end of each month.

The developer makes cash interest payments (column d) to the bank each month. However, because all of the interest carry is borrowed, it becomes part of the loan balance, and because all monthly payments made by the developer are interest only, no reduction of principal occurs.

Such pattern is analogous to an interest-only loan. IO loans require no reduction in loan principal because payments are computed to include interest payments only.

Also note that the interest payments in column (d) are exactly offset by the interest draw in column (b). Thus, the net effect is as if there were no payment to the lender until the entire loan balance is repaid at the end of the construction period. This is analogous to a negative amortization loan with the loan balance increasing by the amount of interest accrued each month.

Flag question: Question 8Question 81 pts

In this case, what is the total draw for this developer? You may want to add one additional column to your excel, and calculate the monthly draw.

What is the total draw for month 4?

Group of answer choices

$1,605,145

$1,305,145

$1,405,145

$1,505,145

Flag question: Spacer

In summary, your excel shows that the loan balance will increase each month by the amount of the project cost draws plus interest borrowed.

The total ending balance, $9,001,416, will be equal to the total construction loan amount at the end of the 12-month period.

What do we want to do with this total ending balance?

This amount will be funded by the permanent lender, thereby taking out the construction lender at that time.

Flag question: Question 9Question 91 pts

Permanent Loan Request

Upon completion of the project, Citadel Life Insurance Company will replace the construction loan with permanent financing, assuming that all conditions in the construction loan and all contingencies outlined in the permanent financing commitment have been met. Remember, the permanent loan terms were predetermined before construction began.

Here is a summary table:

Any additional development costs over $9,001,416 are Southforks responsibility. For a 3 percent loan fee, Citadel Life Insurance Company will provide Southfork with a 10-year mortgage.

Can you use your excel and calculate the monthly payment for this commercial loan?

Hint: it is based on a 25-year amortization schedule at an interest rate of 12 percent.

Group of answer choices

$94,805

$95,805

$96,805

$97,805

Flag question: Question 10Question 101 pts

Equity Investment During Construction Period

Another ingredient in the submission of data to the permanent lender is a pro-forma of construction costs and equity investment. The table above shows a summary. Note that it contains annual estimates for expenditures during the construction period for land acquisition, site improvements, hard costs and soft costs.

Can you take a look at the table, make sure you fully understand all the numbers in the table.

What is the total equity needed for year 0?

Group of answer choices

$2,950,071

$2,850,071

$2,750,071

$2,650,071

Flag question: Question 11Question 111 pts

Use the table in the previous question, for year 0, what would the equity investment cover?

Group of answer choices

land acquisition and loan fee

land acquistion

loan fee and hard cost

land acquistion and hard cost

Flag question: Question 12Question 121 pts

How much equity needed for year 1?

Group of answer choices

$30,800

$31,800

$32,800

$33,800

Flag question: Question 13Question 131 pts

In general, how much total equity investment is needed during construction period?

Group of answer choices

$2,980,871

$2,880,871

$2,780,871

$2,680,871

Flag question: Spacer

Operating Period----Determine EGI

The lease-up or marketing effort should result in 70 percent occupancy during the second year and 95 percent thereafter.

Southfork is estimating a base rent of $15 per square foot of gross leasable area, with average increases based on leases indexed to the CPI of 6 percent per year after the first year of operation (leases are expected to have terms ranging from one to five years).

An overage provision requires tenants to also pay 5 percent of gross sales in excess of a base sales level each month.

In a retail operation, rent is usually divided into two components. The first is a minimum rent per square foot. The other component is called percentage rent. Developers frequently charge percentage rent, calculated as a percentage of the sales of a tenant in excess of a predetermined breakpoint or sales volume. As long as the tenants sales are below the breakpoint, the owner receives only the minimum rent. When a tenants sales increase above the breakpoint, the percentage rent rate is applied to the sales volume in excess of the breakpoint and is added to the minimum rent, thus increasing the total rent. In this way, should the shopping center become very successful, the owner shares in the increased revenue produced by the tenants.

Tenant reimbursements are based on negotiations between the owner and tenants and represent the amount of operating expenses over expense stops for which the tenant is responsible. Hence, base rents, percentage rents, and expenses for which tenants are responsible over some preagreed amount (stop) all represent gross income to the owner of Rolling Meadows.

The table below shows the details.

Flag question: Spacer

Operating Period ---Determine the total expenses

Operating expenses represent the actual expenses that must be paid to operate Rolling Meadows. They are deducted from rents, overage, and tenant reimbursements.

All leases are to be net to the tenant, with a direct pass-through for insurance and property taxes. Tenants will also be billed for their share of common area maintenance (parking lot, circulation space in center, etc.) and utilities.

An additional premium will be added to the utility charge to provide for a replacement reserve on HVAC equipment.

Tenants will pay these expenses to Southfork as reimbursement. Southfork management will, in turn, pay any expenses to third parties as they become due. Southfork will also incur expenses of its own for property management, leasing commissions, and general and administrative expenses that will not be recoverable from tenants. These amounts are deducted from rents, overage, and tenant reimbursements. The projections assume that a sufficient number of leases will be signed at the end of the second year to warrant closing the permanent loan.

Here is a table:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions

Question

How is a futures contract priced?

Answered: 1 week ago