Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs

Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $41,000; design $334,000; and construction oversight $116,550. The cost drivers and estimated use are as follows.

Activities

Cost Drivers

Estimated Use of Cost Drivers per Activity

Initial concept formation Number of project changes 25
Design Square feet 167,000
Construction oversight Number of months 105

(a) Compute the predetermined overhead rate for each activity.

Overhead Rate

Initial concept formation $

per project change
Design $

per square foot
Construction oversight $

Per month

(b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.

Activities

Level

Initial concept formation

Product-levelUnit-levelFacility-levelBatch-level

Design

Batch-levelProduct-levelFacility-levelUnit-level

Construction oversight

Batch-levelFacility-levelUnit-levelProduct-level

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Future Of Audit Keeping Capital Markets Efficient

Authors: Keith Houghton, Christine Jubb, Michael Kend, Juliana Ng

1st Edition

1921666501, 978-1921666506

More Books

Students also viewed these Accounting questions

Question

1. Identify three approaches to culture.

Answered: 1 week ago

Question

2. Define communication.

Answered: 1 week ago