Question
Splish Company budgeted the following cost standards for the current year: Direct materials (2 kg of plastic at $6.00 per kilogram) $12.00 Direct labour (2
Splish Company budgeted the following cost standards for the current year:
Direct materials (2 kg of plastic at $6.00 per kilogram) | $12.00 | ||
Direct labour (2 hours at $12 per hour) | 24.00 | ||
Variable manufacturing overhead | 10.05 | ||
Fixed manufacturing overhead | 6.30 | ||
Total standard cost per unit | $52.35 |
Actual costs for producing 2,730 units were as follows:
Direct materials used | 5,980 | kg | ||
Direct materials purchased (6,580 kg) | $38,164 | |||
Direct labour (6,930 hours) | $67,914 | |||
Variable manufacturing costs | $33,000 | |||
Fixed manufacturing costs | $17,900 |
(d)
Calculate the labour quantity variance.
Labour quantity variance | $enter the labour quantity variance in dollars | select an option UnfavourableNeither favourable nor unfavourableFavourable |
2.Tidex Company is a manufacturer of cleaning detergent. Cleanx is manufactured on a weekly basis. The following standards have been established to produce 10,000 litres of Cleanx:
Standard direct materials used: 10,000 litres of detergent Standard direct material price per litre $4 Actual direct materials used: 12,000 litres Actual direct material price per litre: $4.35 Calculate the Total Direct Materials Budget Variance (TDMBV).
$8,700 Unfavourable.
$12,200 Favourable.
$40,000 Favourable.
$12,200 Unfavourable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started