Question

1 Approved Answer

Stadium Construction Project Problem : What is the project duration ? ACTIVITY IMMEDIATE PREDECESSOR DURATION ( days ) A 1 B A 4 C A

Stadium Construction Project Problem : What is the project duration ? ACTIVITY IMMEDIATE PREDECESSOR DURATION (days ) A 1 B A 4 C A 3 D A 7 E B 6 F CD 2 G EF CH 7 D 9 G.H 424 days 23 days 22 days 21 days 20 days