Question
Standard Cost Card Direct materials, 2.0 meters at $16 per meter $32.00 Direct labor, 1.0 hours at $15 per hour $15.00 Variable overhead, 1.0 hours
Standard Cost Card |
|
Direct materials, 2.0 meters at $16 per meter | $32.00 |
Direct labor, 1.0 hours at $15 per hour | $15.00 |
Variable overhead, 1.0 hours at $9 per hour | $9.00 |
| Total Standard | Quantity or Efficiency | Price or Rate |
| Cost | Variance | Variance |
Direct Materials | $608,000 | $32,000 U | $11,600 F |
Direct Labor | $285,000 | $15,000 U | $4,000 U |
Variable overhead | $171,000 | unknown | $4,000 F |
Required
2. How many meters of direct materials were purchased and used in production? (40,000 Meters)
3. What was the actual cost per meter of material? ($15.71 per meter)
4. How many actual direct labor-hours were worked during the period? (20,000 hours)
5. What was the actual rate per direct-labor hour? ( $15.20 per hour)
6. How many actual variable manufacturing overhead cost was incurred during the period? ($176,000)
I have the answers, I am confused on how to calculate for the SQ, SP, AQ, AP, SH, SR, AH, AR Please help in details
,
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started