Question
Standard Costs, Decomposition of Budget Variances, Direct Materials and Direct Labor EZ Tees Corporation produces T-shirts. The company uses a standard costing system and has
Standard Costs, Decomposition of Budget Variances, Direct Materials and Direct Labor
EZ Tees Corporation produces T-shirts. The company uses a standard costing system and has set the following standards for direct materials and direct labor (for one shirt):
Fabric (1.5 yds. @ $2.80) | $4.20 |
Direct labor (1.1 hr. @ $20) | 22.00 |
Total prime cost | $26.20 |
During the year, EZ Tees produced 9,600 T-shirts. The actual fabric purchased was 14,300 yards at $2.76 per yard. There were no beginning or ending inventories of fabric. Actual direct labor was 10,680 hours at $19.50 per hour.
Required:
Question Content Area
1. Compute the costs of fabric and direct labor that should have been incurred for the production of 9,600 T-shirts.
Direct materials | $fill in the blank 2e7a7705efd6f85_1 |
Direct labor | $fill in the blank 2e7a7705efd6f85_2 |
2. Compute the total budget variances for direct materials and direct labor.
Direct materials | $fill in the blank 2e7a7705efd6f85_3 | FavorableUnfavorable |
Direct labor | $fill in the blank 2e7a7705efd6f85_5 | FavorableUnfavorable |
3. Break down the total budget variance for direct materials into a price variance and a usage variance.
Materials Price Variance | $fill in the blank 2e7a7705efd6f85_7 | FavorableUnfavorable |
Materials Usage Variance | $fill in the blank 2e7a7705efd6f85_9 | FavorableUnfavorable |
Question Content Area
Prepare the journal entries associated with these variances. If an amount box does not require an entry, leave it blank.
Price Variance | Accounts PayableCashCost of Goods SoldDirect Materials Usage VarianceMaterialsWork in Process | - Select - | - Select - |
Accounts ReceivableCashCost of Goods SoldDirect Materials Price VarianceWork in Process | - Select - | - Select - | |
Accounts PayableDirect Materials Usage VarianceFinished GoodsMaterialsWork in Process | - Select - | - Select - | |
Usage Variance | Accounts PayableCashDirect Materials Price VarianceMaterialsOverhead ControlWork in Process | - Select - | - Select - |
Accounts PayableDirect Materials Usage VarianceFinished GoodsOverhead Control Work in Process | - Select - | - Select - | |
Accounts PayableCashDirect LaborMaterialsWork in Process | - Select - | - Select - |
Question Content Area
4. Break down the total budget variance for direct labor into a rate variance and an efficiency variance.
Labor Rate Variance | $fill in the blank 41b32e007fd1047_1 | FavorableUnfavorable |
Labor Efficiency Variance | $fill in the blank 41b32e007fd1047_3 | FavorableUnfavorable |
Question Content Area
Prepare the journal entries associated with these variances. If an amount box does not require an entry, leave it blank.
blank | Accounts PayableCashDirect Materials Price VarianceDirect Materials Usage VarianceMaterialsOverhead ControlWork in Process | - Select - | - Select - |
Accounts PayableCashDirect Labor Efficiency VarianceDirect Materials Price VarianceDirect Materials Usage VarianceMaterialsFinished Goods | - Select - | - Select - | |
Accounts PayableCashDirect Labor Rate VarianceDirect Materials Price VarianceDirect Materials Usage VarianceFinished GoodsMaterials | - Select - | - Select - | |
Direct Labor Efficiency VarianceDirect Labor Rate VarianceFinished GoodsWages PayableWork in Process | - Select - | - Select - |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started