Standard Job Order Costing - Variance Analysis Special order lamps are manufactured in division S. Because of the precise nature of the process a standard
Standard Job Order Costing - | |||||||
Variance Analysis | |||||||
Special order lamps are manufactured in division S. Because of the precise nature of the process a | |||||||
standard cost system has been developed. The following standards are used for the special orders: | |||||||
Standards | |||||||
Lamp Kits | $16.000000 | per lamp | |||||
Direct Labor | 2.400000 | per lamp (4 lamps/hr.) | |||||
Variable Overhead | 0.250000 | per lamp (4 lamps/hr.) | |||||
** | Fixed Overhead | 10.000000 | per lamp | ||||
Total | $28.650000 | ||||||
** Fixed overhead is based on expected production of 4,012 customized lamps each month. | |||||||
To keep records of the actual cost of a job, a Job Order Cost System has been developed. Entries | |||||||
are made to the Job Order System at actual cost (overhead is applied based on actual labor hours) | |||||||
while entries are made to the accounting system at standard. Variance analysis is used to analyze the | |||||||
differences. | |||||||
Job Order Costing Section | |||||||
On January 1, 20x2, Division S began Job 1101 for the Client, THE BIG CHILDREN STORE. The | |||||||
job called for 4,000 customized lamps. The following set of transactions occurred from | |||||||
January 5 until the job was completed: | |||||||
5-Jan | Purchased 4,100 Lamp Kits @ $16.70 per kit. | ||||||
9-Jan | 4,100 sets of Lamp Kits were requisitioned. | ||||||
17-Jan | Payroll of 610 Direct Labor Hours @ $9.75 per hour. | ||||||
30-Jan | Payroll of 660 Direct Labor Hours @ $10.00 per hour. | ||||||
30-Jan | 3,988 lamps were completed and shipped. All materials requisitioned were | ||||||
used or scrapped. | |||||||
Month End Overhead Information | |||||||||||||
Actual Variable Overhead | $ 1,447.80 | ||||||||||||
Actual Fixed Overhead | $ 40,623.45 | ||||||||||||
How many Lamps were completed? |
| ||||||||||||
| |||||||||||||
Note: Show favorable variances as negative numbers |
| ||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
What was the total material price variance for the Lamp Kits purchased? |
| ||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
What was the material usage variance for Lamp Kits? |
| ||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
What was the direct labor efficiency variance ? |
| ||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
What was the direct labor rate variance? |
| ||||||||||||
| |||||||||||||
| |||||||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started