Question
1 Approved Answer
Standard Labor Rate: $15 per hour; Standard Hours per Unit: 4 hours; Actual Labor Rate: $14 per hour; Actual Hours Worked: 2,000 hours. Requirements :
- Standard Labor Rate: $15 per hour; Standard Hours per Unit: 4 hours; Actual Labor Rate: $14 per hour; Actual Hours Worked: 2,000 hours.
- Requirements:
- Calculate the labor rate variance and labor efficiency variance.