Standard labour cost per unit $45 (3 hours at $15/hour). The company incurred actual direct labour cost of $4,300 when it produced 100 units of
Standard labour cost per unit $45 (3 hours at $15/hour). The company incurred actual direct labour cost of $4,300 when it produced 100 units of finished product this month. It took them 275 hours to produce all 100 units. Based on this calculate the direct labour rate variance. If unfavourable enter answer as a negative.