Question
Stanford Company has contracted to build for the City of New London a new courthouse. The estimated cost of the jail is $6,000,000, and the
Stanford Company has contracted to build for the City of New London a new courthouse. The estimated cost of the jail is $6,000,000, and the contract price is $9,000,000. The courthouse took three years to complete as follows:
2014 2015 2016 Costs to date $1,200,000 $4,000,000 $6,400,000 Cost to complete $4,800,000 $2,400,000 $0
Amounts billed to date $1,400,000 $5,800,000 $9,000,000 Amounts collected to date $1,300,000 $4,300,000 $9,000,000
Record all journal entries necessary for each of the three years below: (2014, 2015, 2016)
2014 Dr. Cr.
2015
2016
Give the balance sheet presentation of the construction at the end of 2014.
Assume that Stanford uses the completed contract method. Determine the amount of revenue and expense to be recognized in: 2014 2015 2016
Revenue Expense
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started