Star Construction Corp. has a contract to construct a building for $10,992,600. The building is controlled by the customer throughout the term of the contract.

Star Construction Corp. has a contract to construct a building for $10,992,600. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,898,600. Construction commenced on 4 February 20X5. Actual costs were in line with estimated costs for 20X5 and 20X6. In 20X7, actual costs exceeded estimated costs by $137,400.

Total construction costs incurred in each year were as follows:

20X5 $2,710,800

20X6 $4,518,000

20X7 $1,807,200

Billings each year were as follows:

20X5 $2,309,000

20X6 $4,919,200

20X7 $3,764,400

Calculate and present the revenues and gross profit for the construction project for each of the three years assuming the company uses inputs to measure progress and revenue recognition.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Benfords Law

Authors: Mark J. Nigrini

1st Edition

1118152859, 9781118152850

More Books

Students also viewed these Accounting questions