Question
Star Construction Corp, has contact to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total
Star Construction Corp, has contact to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total cost to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20X5. Actual costs were in line with estimated costs for 20X5 and 20X6. In 20X7, actual costs exceeded the estimated cost by $150,000.
20X5 $2,700,000
20X6 $4,500,000
20X7 $1,800,000
Billings each year were as follows.
20X5 $2,300,000
20X6 $4,900,000
20X7 $3,750,000
1. Calculate the revenue and gross profit for the construction project each of the three years assuming the company uses inputs to measure progress.
2. Prepare the journal entries for revenue recognition for each year and for contract completion in 20X7
3. Prepare the journal entries for revenue recognition for each year and for contact completion in 20X7, if the customer did not take control of the asset until the building was fully constructed and title transferred.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started