Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Start A B 3 K L M N O P D 11 Activity J E F 6 H Question 2.3 Consider the network described
Start A B 3 K L M N O P D 11 Activity J E F 6 H Question 2.3 Consider the network described in the table below. (a) Which is the CP? (b) Calculate the duration of the CP. (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time-units, what would be the impact on the project duration? Immediate Predecessor(s) -- J J J K, M K, M L, N 6 Pessimistic 15 9 10 3 9 10 10 K End Probable 10 8 6 3 5 7 8 Optimistic 8 7 5 3 1 4 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will be completed in more than 28 time units. Question 2.4 The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity A B C D E F G H Normal Duration (hours) 2 3 5 3 6 1 7 10 Normal Cost ($) 10 15 25 20 30 5 35 50 Crash Duration Crash (hours) 2 2 4 1 4 1 6 7 Cost (S) 0 23 30 24 45 0 50 62 Immediate Predecessors None A B C C C,E F D,G Question 2.1 Walmart Canada debuted a new checkout system called "fast lane" that lets customers avoid cashiers and registers. Here's how it works: My Walmart users scan items with their phones as they shop. Once a user is finished shopping, they click "checkout" to receive a barcode. Next, the customer scans the order barcode at one of four scanning stations in the fast lane. This action charges the credit card the My Walmart user has on file. Finally, just before exiting the store, customers present their mobile receipts to a worker tending the fast lane. The system has debuted in a newly opened store in Toronto that Walmart says will serve as a prototype for future store renovations. Assume the new fast lane setup will replace 2 old cashier lanes that were staffed by a cashier and bagger on each lane. One worker mans all 4 scanning stations (answering questions, checking for un-scanned items, taking coupons, etc). Checkout on the new lanes takes 2 minutes (customers bag their own orders) while checkout with the old lanes took only 45 seconds. In addition, the electricity costs for both setups are $0.05 per checkout while bagging (material) costs are $0.10 per checkout with the old system and $0.15 for the new system. The new lanes also require $100/shift in capital costs. Assume that the lanes are always in use for 8 hours per day (1 shift) and that a worker makes $10/hour. (a) How many checkouts did the old system provide in a shift? (b) How many checkouts does the new system provide? (c) What is the multifactor productivity for each system? Question 2.2 Below is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the network.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started