Stellar Construction entered into a contract to build a commercial building for $3,600,000. Stellar Construction uses the percentage-of-completion method for recognizing revenue on the project.
Stellar Construction entered into a contract to build a commercial building for $3,600,000. Stellar Construction uses the percentage-of-completion method for recognizing revenue on the project. Construction began in September of 2018 and the building was completed in June of 2020. The company provided the following additional information on the project.
Prepare the journal entries for the balance sheet in each year of the project.
2018 2019 2020 Costs incurred to date $ 725,000 $ 2,100,000 $ 3,400,000 Estimated costs to complete 2,175,000 $ 1,400,000 $ Billings during the year 800,000 $ 1,650,000 1,150,000 Cash collected during the year $ 450,000 $ 1,900,000 1,200,000Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started