Question

1 Approved Answer

Stop day at a work center = Start day + Duration Start day at work center 2 0 = Max ( Stop day at workstation

Stop day at a work center = Start day + Duration
Start day at work center 20= Max (Stop day at workstation 10 for current job, Stop day at workstation 20 for previous job)