Stuart Conaty 2 0 2 3 1 CIVEN 3 0 0 9 0 Professional Engineering for Civil and Structural Engineers Assignment 2 0 2 3
Stuart Conaty CIVEN
Professional Engineering for Civil and
Structural Engineers
Assignment
Given the data set out in the table below please complete the tasks numbered to
following.
Task Successor Tasks Duration
Start ABC
A DE
B E
C I
D F
E G
F H
G HI
H Finish
I Finish
Complete the network analysis for the data given above.
Produce the resulting Gantt chart.
Identify the critical path.
If the execution of Task G was delayed by five due to an Employer risk eg late possession of
a part of the site in the circumstances is the Contractor entitled to an extension of time EOT to
complete the project and if so how many days EOT? Please explain your answer.
Task H is delayed by three days due to an Employer risk eg late possession of a part of the
site is the Contractor entitled to an extension of time EOT to complete the project and if so
how many days EOT? Please explain your answer.
What difference, if any, would knowledge of a concurrent delay of seven days in completing
Task C because of a contractor HR problem have to you answer at above? Please explain your
answer
The HR issue deteriorates, and Task C is delayed by a further eight days what impact, if any,
would this have on the contractor's entitlement to an extension of time for the delay to Task G
referred to at point above? Please explain your answer.
Complete a revised network analysis taking account of the cumulative effect of each of the
delays set out in points to above.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started