Study Session 1.You are a project manager of a project to develop a new wireless feature. The feature is made up of the phases in

Study Session

1.You are a project manager of a project to develop a new wireless feature. The feature is made up of the phases in the table below. Each phase is planned to be completed one after the other. Today is the end of Month 5

CAP

Duration

Budget

Requirements

1 months

$ 10,000

Architecture

1 month

$ 10,000

Design

1 month

$ 10,000

Code

2 months

$ 20,000

Testing

1 months

$ 10,000

Using the Project status chart below, calculate EV, etc

Task

Month 1

Month 2

Month 3

Month 4

Month 5

Month 6

Status at end of Month 5

Requirements

S-------F

Complete, Spent $10,000

Architecture

S----PF

--F

Complete, spend $12,000

Design

PS-S-PF

--F

Complete, Spend $ 12,500

Code

PS----S-

-----PF

25% Complete, Spend $ 7000

Testing

PS---PF

Not Started

What is

Calculation

Answer

Interpretation of the answer

BCWS or PV

BCWP or EV

ACWP or AC

BAC

CV

CPI

SV

SPI

EAC

ETC

VAC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Revenue Service Status Of GAO Financial Audit And Related Financial Management Recommendations

Authors: Government Accountability Office

1st Edition

1492351571, 978-1492351573

More Books

Students also viewed these Accounting questions