Study Session 1.You are a project manager of a project to develop a new wireless feature. The feature is made up of the phases in
Study Session
1.You are a project manager of a project to develop a new wireless feature. The feature is made up of the phases in the table below. Each phase is planned to be completed one after the other. Today is the end of Month 5
CAP | Duration | Budget |
Requirements | 1 months | $ 10,000 |
Architecture | 1 month | $ 10,000 |
Design | 1 month | $ 10,000 |
Code | 2 months | $ 20,000 |
Testing | 1 months | $ 10,000 |
Using the Project status chart below, calculate EV, etc
Task | Month 1 | Month 2 | Month 3 | Month 4 | Month 5 | Month 6 | Status at end of Month 5 |
Requirements | S-------F |
|
|
|
|
| Complete, Spent $10,000 |
Architecture |
| S----PF | --F |
|
|
| Complete, spend $12,000 |
Design |
|
| PS-S-PF | --F |
|
| Complete, Spend $ 12,500 |
Code |
|
|
| PS----S- | -----PF |
| 25% Complete, Spend $ 7000 |
Testing |
|
|
|
|
| PS---PF | Not Started |
What is | Calculation | Answer | Interpretation of the answer |
---|---|---|---|
BCWS or PV
|
|
|
|
BCWP or EV
|
|
|
|
ACWP or AC
|
|
|
|
BAC
|
|
|
|
CV
|
|
|
|
CPI
|
|
|
|
SV
|
|
|
|
SPI
|
|
|
|
EAC
|
|
|
|
ETC
|
|
|
|
VAC
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started