Submit for grading: 1.Chapter 7, Problems, #14 14. You are the manager of a project to improve a billing process at your firm. Table 7.7

Submit for grading:

1.Chapter 7, Problems, #14

14. You are the manager of a project to improve a billing process at your firm. Table 7.7 contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after week 12.

a. What is the minimum-cost schedule for this project?

b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part (a)?

image text in transcribed
Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A 4 5,000 8,000 B 8,000 10,000 C A 4,000 4,000 D B 6 3 6,000 12,000 B, C 4,000 7,000 F D - 6 4,000 7,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law Of Tort

Authors: John Cooke

14th Edition

1292251360, 978-1292251363

More Books

Students also viewed these Law questions

Question

Relax your shoulders

Answered: 1 week ago