Summaries for some subsets of the activities identified in the overall project network are called: Select one: a . Compressed activities. b . Ladder activities.
Summaries for some subsets of the activities identified in the overall project network are called:
Select one:
a
Compressed activities.
b
Ladder activities.
c
Negative float activities.
d
Hammock activities.