Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presented below: Bid price $ 450,000 Contract costs: 2020 (180,000)
Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presented below:
Bid price | $ 450,000 | |
Contract costs: | 2020 | (180,000) |
2021 | (195,000) | |
Estimated cost to complete: | ||
12/31/2020 | $ 220,000 | |
12/31/2021 | 0 |
BCC recognizes revenue over time according to percentage of completion for this contract. The correct amount of revenue recognized in 2020 should be ____ and the correct gross profit recognized in 2020 should be ____.
fill in the blanks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started