Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2013, are presented below: Bid price $450,000 Contract cost: 2012 (180,000) 2013

Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2013, are presented below:

Bid price $450,000
Contract cost: 2012 (180,000)
2013 (195,000)
Gross profit: 75,000
Estimated cost to complete:
12/31/2012 $200,000
12/31/2013 0

Assuming BCC used the completed contract method to recognize revenue, what would gross profit have been in 2012 and 2013 (rounded to the nearest thousand)?

2012

2013

a. $36,000 $39,000
b. $30,000 $45,000
c. $70,000 $5,000
d. $0 $75,000

Choice A

Choice B

Choice C

Choice D

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Internal Auditing Handbook

Authors: K. H. Spencer Pickett

3rd Edition

0470518715, 978-0470518717

More Books

Students also viewed these Accounting questions

Question

Stages of a Relationship?

Answered: 1 week ago