Summerlin Company budgeted 4,700 pounds of material costing $4.00 per pound to produce 2,400 units The company actually used 5,200 pounds that cost $4.10 per
Summerlin Company budgeted 4,700 pounds of material costing $4.00 per pound to produce 2,400 units The company actually used 5,200 pounds that cost $4.10 per pound to produce 2,400 units. What is the direct materials price variance? O$520 unfavorable. $2.000 unfavorable. O $2.520 unfavorable. O $470 unfavorable. O $2.050 unfavorable