Question

1 Approved Answer

Super Good Corp. contracted to build a bridge for $ 5,000,000. Construction began in 2020 and was completed in 2021. Data relating to the construction

Super Good Corp. contracted to build a bridge for $ 5,000,000. Construction began in 2020 and was completed in 2021. Data relating to the construction are:

2020 2021

Costs incurred....................................................................... $ 1,620,000 $ 1,400,000

Estimated costs to complete................................................... 1,380,000

Instructions

Using the percentage-of-completion method and the cost-to-cost basis

How much revenue should be reported for 2020? Show your calculation.

Prepare the journal entry to record progress billings of $ 1,700,000 during 2020.

Prepare the journal entry to record the revenue and gross profit for 2020.

How much gross profit should be reported for 2021? Show your calculation

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions