Support Department Cost Allocation: Comparison of Methods of Allocation Bender Automotive Works Inc. manufactures a variety of front-end assemblies for automobiles. A front-end assembly is

Support Department Cost Allocation: Comparison of Methods of Allocation

Bender Automotive Works Inc. manufactures a variety of front-end assemblies for automobiles. A front-end assembly is the unified front of an automobile that includes the headlamps, fender, and surrounding metal/plastic. Bender has two producing departments: Drilling and Assembly. Usually, the front-end assemblies are ordered in batches of 100.

Two support departments provide support for Bender's producing departments: Maintenance and Power. Budgeted data for the coming quarter follow. The company does not separate fixed and variable costs.

Support Departments Producing Departments
Maintenance Power Drilling Assembly
Overhead costs $320,000 $400,000 $163,000 $90,000
Machine hours - 22,500 30,000 7,500
Kilowatt-hours 40,000 - 36,000 324,000
Direct labor hours - - 5,000 40,000

The predetermined overhead rate for Drilling is computed on the basis of machine hours. Direct labor hours are used for Assembly.

Recently, a truck manufacturer requested a bid on a 3-year contract that would supply front-end assemblies to a nearby factory. The prime costs for a batch of 100 front-end assemblies are $1,817. It takes two machine hours to produce a batch in the drilling department and 50 direct labor hours to assemble the 100 front-end assemblies in the assembly department.

Bender's policy is to bid full manufacturing cost, plus 15%.

1. Prepare bids for Bender by using each of the following allocation methods:

(a) Direct method. (Note: Round allocation ratios, and the job cost components to two decimal places, if rounding is required.)

Bender Automotive Works Inc.
Direct Method
Prime costs $
Drilling
Assembly
Total cost $
Markup
Bid price

$

(b) Sequential method, allocating power costs first. (Note: Round allocation ratios, and the job cost components to two decimal places, if rounding is required.)

Bender Automotive Works Inc.
Sequential Method
Prime costs $
Drilling
Assembly
Total cost $
Markup
Bid price $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

1. Discuss the four components of language.

Answered: 1 week ago

Question

a. How many different groups were represented?

Answered: 1 week ago