Question

1 Approved Answer

Suppose a product must go through an assembly line where the first step takes an average of 10 minutes. The next step can be done

Suppose a product must go through an assembly line where the first step takes an average of 10 minutes. The next step can be done by any one of three machines, each of which takes an average of 20 minutes per product. Lastly, the assembly step takes 5 minutes and is done by a human. Assume that no work-in-process (WIP) is permitted beyond that actually being worked on at each process step (i.e., there are no buffers between process steps).

a. What is the capacity of the process, and what is the bottleneck?

b. What is the average theoretical flow time (i.e., without including waiting for service)?

c. If the average demand is 10 units/hour, what is the throughput rate of the process?

d. What is the utilization of the assembly operator?



Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Spreadsheet Modeling And Decision Analysis A Practical Introduction To Business Analytics

Authors: Cliff T. Ragsdale

8th Edition

130594741X, 978-1337517317, 1337517313, 978-1305947412

More Books

Students also viewed these General Management questions