Suppose that the following estimates of activity times ( in weeks ) were provided for the network shown above. Activity Optimistic Most Probable Pessimistic A

Suppose that the following estimates of activity times (in weeks) were provided for the network shown above.
Activity Optimistic Most Probable Pessimistic
A 4.05.06.0
B 2.53.03.5
C 6.07.08.0
D 5.05.59.0
E 5.07.09.0
F 2.03.04.0
G 8.010.012.0
H 6.07.014.0
What is the probability that the project will be completed within the following time frames? (Round your answers to four decimal places. You may need to use the appropriate technology to answer this question.)
(a)
Within 19 weeks?
(b)
Within 22 weeks?
(c)
Within 23 weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Building Management Skills An Action First Approach

Authors: Richard L. Daft, Dorothy Marcic

1st Edition

0324235992, 9780324235999

More Books

Students also viewed these General Management questions

Question

Describe the various forms of economic integration in Europe. LO.1

Answered: 1 week ago