Suppose that the following processes arrive for execution at the times indicated. Each process will run for the amount of time listed. In answering the

Suppose that the following processes arrive for execution at the times indicated. Each process will run for the amount of time listed. In answering the questions, use non-preemptive scheduling, and base all decisions on the information you have at the time the decision must be made.

Process Arrival Time Burst Time Priority level Size of job

P1 0.0 8 3 15k

P2 0.4 4 2 10k

P3 1.0 1 1 25k

Calculate the average turnaround time and produce the Gantt charts for these processes using the following dispatch algorithms i. Round robin with quantum of 2 secs

ii Strict Priority

iii. Shortest Remaining time First

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Marketing The Ultimate Marketing Tool

Authors: Edward L. Nash

1st Edition

0070460639, 978-0070460638

More Books

Students also viewed these Databases questions

Question

What benefits are we looking to gain by using external providers?

Answered: 1 week ago