Suppose the critical path in the PERT method has mean 50 days and variance 100. Then the probability that the project completion time will be

Suppose the critical path in the PERT method has mean 50 days and variance 100.

Then the probability that the project completion time will be 70 days or less is approximately

Group of answer choices

a. 98%

b. 50%

c .100%

The PERT method of computing the project completion time assumes that

Group of answer choices

a. the duration of each path is a bell curve.

b. the duration of each activity is a bell curve.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David M Kroenke, Randall J Boyle

7th Edition

0134402197, 9780134402192

More Books

Students also viewed these General Management questions

Question

1. To understand how to set goals in a communication process

Answered: 1 week ago