Question

1 Approved Answer

Suppose the normal direct costs for completing a project in 65 days are $75,000. The client wants the project delivered by day 58, and has

Suppose the normal direct costs for completing a project in 65 days are $75,000.

The client wants the project delivered by day 58, and has indicated there will be financial penalties for delivery after day 58.

You have been given the indirect costs and the penalty costs for the project as follows:

Project duration (days) Indirect costs Penalty costs
65 $10,000 $5,000
64 $9,750 $4,000
63 $9,500 $3,000
62 $9,250 $2,000
61 $9,000 $1,000
60 $8,750 $500
59 $8,500 $250
58 $8,250 $0

You also know that the activities to crash, to complete the project early are as follows: Crash A for up to 2 days at $850/day

Crash J for up to 2 days at $600/day Crash P for up to 4 days at $800/day

What is the most financially beneficial date to complete the project? Demonstrate why by showing your calculations. (5 marks).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Reporting International Standards

Authors: Graham Eaton

1st Edition

0750662379, 978-0750662376

More Books

Students also viewed these Accounting questions