Suppose there is an order for 200 of gear shaft SG 123. The due date is day 158. The route sheet, shown in Figure 1,

Suppose there is an order for 200 of gear shaft SG 123. The due date is day 158. The route sheet, shown in Figure 1, gives information about the operations to be performed and the setup and run times. The work center file, shown in Figure 2, gives lead time data for each work center. Calculate the start and finish dates for each operation. Use the following scheduling rules.

a. Operation times are rounded up to the nearest 8 hours and expressed as days on a

one-shift basis. That is, if an operation takes 6.5 standard hours, round it up to 8 hours, which represents one day.

b. Assume an order starts at the beginning of the day and finishes at the end of a day. For example, if an order starts on day 1 and is finished on day 5, it has taken 5 days to complete. If move time is 1 day, the order will be available to the next workstation at the start of day 7.

Figure 1 Routing file

Part Name: Gear Shaft Part Number: SG123

Drawing Number: D123X

Operations No. Work Center S/U Time(standard hours Run Time/Piece(standard hours) Operation
10 12 1.50 0.20 Turn Shaft
20 14 0.50 0.25 Mill Slot
30 17 0.30 0.05 Drill 2 holes
40 03 0.45 0.10 Grind
50 Stores Inventory

Figure 2: Lead time data from work center file.

Operations Number Work Center Arrival Date Queue(days) Operations(days) Wait(days) Finish Date
10 12 I. 4 A. 1 E.
20 14 J. 2 B. 1 F.
30 17 K. 5 C. 1 G.
40 03 L. 4 D. 1 H.
50 Stores 158

Please fill in the blank from A to L

The order must arrive at work center 12 on which day?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cash, Corruption And Economic Development

Authors: Vikram Vashisht

1st Edition

1032096888, 9781032096889

More Books

Students also viewed these Accounting questions

Question

What role do hormone levels play in mood?

Answered: 1 week ago

Question

Appreciate important legal implications of performance appraisals

Answered: 1 week ago