Suppose we are formulating a Master Production Schedule (MPS) for an item. Week 0 projected on-hand is 80 units. The lot-size policy for this item
Suppose we are formulating a Master Production Schedule (MPS) for an item. Week 0 projected on-hand is 80 units. The lot-size policy for this item calls for L4L ordering. Lead time for this item is one week. There are no safety stock requirements.
Here are the demand forecast and the booked orders for this item ...
Week | ||||||
1 | 2 | 3 | 4 | 5 | 6 | |
Forecast | 60 | 45 | 45 | 45 | 45 | 60 |
Booked | 63 | 43 | 30 | 10 | 0 | 0 |
What will be the order size of the first MPS Start Quantity that is needed?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started