Suppose we are formulating a Master Production Schedule (MPS) for an item. Week 0 projected on-hand is 80 units. The lot-size policy for this item

Suppose we are formulating a Master Production Schedule (MPS) for an item. Week 0 projected on-hand is 80 units. The lot-size policy for this item calls for L4L ordering. Lead time for this item is one week. There are no safety stock requirements.

Here are the demand forecast and the booked orders for this item ...

Week
1 2 3 4 5 6
Forecast 60 45 45 45 45 60
Booked 63 43 30 10 0 0

What will be the order size of the first MPS Start Quantity that is needed?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

11th Edition

9780132997621, 132149117, 132997622, 978-0132149112

Students also viewed these General Management questions