Suppose you are considering crashing the following project. Use the information in the table below to answer the following questions. Normal Crashed Activity Predecessors Duration

Suppose you are considering crashing the following project. Use the information in the table below to answer the following questions.
Normal
Crashed
Activity
Predecessors
Duration
Cost ($)
Duration
Cost ($)
A
-
4 days
1,000
3 days
2,000
B
A
6 days
1,800
3 days
3,000
C
A
4 days
2,500
3 days
4,000
D
B, C
9 days
2,700
6 days
6,500
E
B
8 days
2,400
6 days
4,500
F
D
5 days
3,500
3 days
7,000
G
E, F
2 days
2,400
1 day
3,000
What is the Crashing Costs per Day (cost slope) for activity E, and is it on the critical path?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions

Question

Which event marked the official end of the American civil war ?

Answered: 1 week ago