Suppose you have the following information:
Demand rate (D)=790 units per hour
Lead time(T)=38 hours
Container capacity (C)=500 units
Safety factor (x)=25%
Part 2
The number of kanban production cards is enter your response here. (Enter your response rounded up to the next whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Management

Authors: Ricky Griffin

10th Edition

9780357517345

Students also viewed these General Management questions