Question
Swifty Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs.
Swifty Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations.
Standard | Custom | |||
Direct labor costs | $50,000 | $100,000 | ||
Machine hours | 1,200 | 1,200 | ||
Setup hours | 120 | 390 |
Total estimated overhead costs are $299,100. Overhead cost allocated to the machining activity cost pool is $192,000, and $107,100 is allocated to the machine setup activity cost pool.
A) Compute the overhead rate using the traditional (plantwide) approach. (Round answer to 2 decimal places, e.g. 12.25.)
Predetermined overhead rate __% of direct labor.
B) Compute the overhead rates using the activity-based costing approach.
Machining $____ per machine hr
Machine setup $____ per setup hr
C) Determine the difference in allocation between the two approaches.
Step by Step Solution
3.40 Rating (153 Votes )
There are 3 Steps involved in it
Step: 1
a Predetermined overhead rate 19940 of direct labor cost Workings Computation of overhead rate using ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started