Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Swoosh Snowboard Company must set up an assembly line for snowboards. Forecasts show that 6 4 0 units per day should be produced. The plant

Swoosh Snowboard Company must set up an assembly line for snowboards. Forecasts show that 640 units per day should be produced. The plant operates two 8-hour shifts each day and runs the line continuously during both shifts. The tasks required, task times, and precedence relationships are as follows:
Task Time (seconds) Predecessors
A 40
B 32 A
C 34 A
D 39
E 29 B
F 45 D
G 50 C, E, F
H 35 G
What is the takt time?
What is the theoretical number of workstations?
Assign the tasks to the workstations to balance the line using the longest operating time rule.
What is the efficiency of the balanced line?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Aviation Marketing And Management

Authors: C. Daniel Prather

3rd Edition

9781575243016

More Books

Students also viewed these General Management questions

Question

How is communication defi ned?

Answered: 1 week ago

Question

What are the benefi ts of studying communication?

Answered: 1 week ago