Symphony Electronics produces wireless speakers for outdoor use on patios, decks, etc. Their most popular model is the All WeatherSymphony Electronics produces wireless speakers for
Symphony Electronics produces wireless speakers for outdoor use on patios, decks, etc. Their most popular model is the All WeatherSymphony Electronics produces wireless speakers for outdoor use on patios, decks, etc. Their most popular model is the All Weather
and requires four separate XL components per unit. The company is now planning raw material needs for the second quarter. Sales
of the All Weather are the highest in the second quarter of each year as customers prepare for the summer season. The company has
the following inventory requirements:
a The finished goods inventory on hand at the end of each month must be equal to units plus of the next month's sales.
The finished goods inventory on March is budgeted to be units.
b The raw materials inventory on hand at the end of each month must be equal to of the following month's production needs for
raw materials. The raw materials inventory on March for XL is budgeted to be components.
c The company maintains no work in process inventories.
A sales budget for the All Weather speaker is as follows:
Required:
Prepare a production budget for the All Weather for April, May, June and July.
Answer is complete and correct.
Prepare a direct materials purchases budget showing the quantity of XL components to be purchased for April, May and June
and for the quarter in total.
Answer is complete but not entirely correct.
and requires four separate XL components per unit. The company is now planning raw material needs for the second quarter. Sales
of the All Weather are the highest in the second quarter of each year as customers prepare for the summer season. The company has
the following inventory requirements:
a The finished goods inventory on hand at the end of each month must be equal to units plus of the next month's sales.
The finished goods inventory on March is budgeted to be units.
b The raw materials inventory on hand at the end of each month must be equal to of the following month's production needs for
raw materials. The raw materials inventory on March for XL is budgeted to be components.
c The company maintains no work in process inventories.
A sales budget for the All Weather speaker is as follows:
Required:
Prepare a production budget for the All Weather for April, May, June and July.
Answer is complete and correct.
Prepare a direct materials purchases budget showing the quantity of XL components to be purchased for April, May and June
and for the quarter in total.
Answer is complete but not entirely correct. Symphony Electronics produces wireless speakers for outdoor use on patios, decks, etc. Their most popular model is the All
Weather and requires four separate XL components per unit. The company is now planning raw material needs for the
second quarter. Sales of the All Weather are the highest in the second quarter of each year as customers prepare for the
summer season. The company has the following inventory requirements:
a The finished goods inventory on hand at the end of each month must be equal to units plus of the next
month's sales. The finished goods inventory on March is budgeted to be units.
b The raw materials inventory on hand at the end of each month must be equal to of the following month's production
needs for raw materials. The raw materials inventory on March for XL is budgeted to be components.
c The company maintains no work in process inventories.
A sales budget for the All Weather speaker is as follows:
Required:
Prepare a production budget for the All Weather for April, May, June and July.
Prepare a direct materials purchases budget showing the quantity of XL components to be purchased for April, May
and June and for the quarter in total.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started