Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Table 1 lists seven potential projects. The table shows the NPV, energy efficiency measured by cost savings, and a risk amount that may be lost

Table 1 lists seven potential projects. The table shows the NPV, energy efficiency measured by cost savings, and a risk amount that may be lost considering the possibility of project failure or from a delayed completion time. The firm has a total amount of $15m available for the entire building renovation. The firm is questioning which projects should be undertaken?

One of the benefits of performing previous projects is that the company can learn from its mistakes. A previous retrofit project is listed in Table 2. It shows the activities for the project, along with its predecessor activities, and activity times.

As mentioned previously, every investor wants the firm to reduce the project start to completion time; an effective project manager knows the tricks of the trade to reduce project length. Table 3 lists data that the PM could use when making project decisions related to shortening the project. A project manager from this previous project, George Watkins, was looking at the tables of data and exclaimed aloud, if I had only known, I wouldnt have agreed that we could finish the project in 38 weeks that our investors demanded, but at least I know now how to select the correct activities when shortening a project.

Table 1. List of Potential Projects

Project Description

Project

Cash Required

NPV

Reduced Cost of Energy

Risk

A/C and Heat Controls

1

$2,500

$8,000

$9,000

$(1,200)

Power Generation

2

$3,000

$7,500

$7,000

$(1,300)

Chiller Plant

3

$3,500

$10,000

$8,000

$(3,000)

Lighting

4

$4,500

$12,000

$5,800

$(5,000)

Plumbing

5

$5,000

$16,000

$6,000

$(4,000)

Windows

6

$6,000

$19,500

$5,500

$(18,000)

Roof

7

$7,000

$22,000

$4,000

$(15,000)

Table 2. Previous Project

Activity Description

Activity

Time Estimates (Weeks)

Immediate Predecessors

Optimistic

Most Likely

Pessimistic

Requirements

A

2

3

4

Market Assessment

B

4

7

10

A

Design

C

5

6

9

A

Development

D

6

7

16

C

Testing

E

7

9

10

D

Revising

F

4

5

6

B E

Documentation

G

3

6

10

D

Quality

Assurance

H

2

4

7

C E

Pricing

I

2

2

2

B

Installation

J

3

4

14

F G H I

Project Handoff

K

2

3

4

J

Table 3. Crashing Data

Activity Designation

Crash Time

(Weeks)

Normal Cost ($)

Crash Cost ($)

A

3

10,000

10,000

B

6

20,000

25,000

C

5

15,000

30,000

D

6

45,000

65,000

E

8

10,000

20,000

F

4

15,000

18,000

G

4

20,000

30,000

H

3

10,000

15,000

I

2

5,000

5,000

J

5

40,000

50,000

K

2

15,000

25,000

Questions

1. Crash the project by three weeks. (Excel may prove useful for this question)

2. What is the duration of the project prior to crashing?

3. Which activities did you crash and why?

4. What is the additional cost to crash the project by three weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Statements

Authors: Inc. BarCharts

1st Edition

1423223837, 978-1423223832

More Books

Students also viewed these Finance questions