Question

1 Approved Answer

table [ [ a . Select paint color, 2 days, ] , [ b . Calculate square footage of area to be painted, 1

\table[[a. Select paint color,2 days,],[b. Calculate square footage of area to be painted,15 minutes,],[c. Buy paint,1 hour,a, b],[d. Buy drop cloths, brushes, rollers, TSP, tape,1 hour,],[e. Wash walls with TSP,2 hours,d],[f. Remove lights, plug covers and switch covers,30 minutes,],[g. Tape walls and windows alongside trim,1 hour,d],[h. Paint trim,4 hours,c, d, e, g],[i. Let trim paint dry,3 hours,h],[j. Remove wall tape,15 minutes,i],[k. Tape trim alongside walls,1 hour,d, i],[I. Paint walls,3 hours,c, d, e, f, g, h, k],[m. Let wall paint dry,2 hours,I],[n. Remove trim tape and window tape,15 minutes,m],[o. Replace lights, plug covers and switch covers,30 minutes,m],[p. Clean brushes, rollers,30 minutes,I],[q. Dispose of drop cloths, tape,15 minutes,n]]
What is the completion time?
days hr
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Conceptual Database Design An Entity Relationship Approach

Authors: Carol Batini, Stefano Ceri, Shamkant B. Navathe

1st Edition

0805302441, 978-0805302448

More Books

Students also viewed these Databases questions

Question

=+1. How should performance be assessed for individuals?

Answered: 1 week ago