Question

1 Approved Answer

table [ [ ID , Activity,Predecessor,Duration ] , [ A , Prepare Site,None, 2 ] , [ B , Pour Foundation,A , 3 ]

\table[[ID,Activity,Predecessor,Duration],[A,Prepare Site,None,2],[B,Pour Foundation,A,3],[C,Erect Frame,B,4],[D,Roof,C,4],[E,Windows,C,1],[F,Doors,C,1],[G,Electrical,C,3],[H,Rough-In Frame,D,E,F,2],[I,Door Opener,F, G,1],[J,Paint,H, I,1],[K,Clean Up,2,]]This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the project below.
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 21 days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than the agreed 21 days.
Draw a project network given the information below. Then, do the following:
1. Complete the forward and backward pass
2. Determine the critical path
3. Compute the Total slack for all activities
4. Determine which activities have free float
Then answer the following questions.\table[[ID,Activity,Predecessor,Duration],[A,Prepare Site,None,2],[B,Pour Foundation,A,3],[C,Erect Frame,B,4],[D,Roof,C,4],[E,Windows,C,1],[F,Doors,C,1],[G,Electrical,C,3],[H,Rough-In Frame,D,E,F,2],[I,Door Opener,F, G,1],[J,Paint,H, I,1],[K,Clean Up,2,]]
Question 1
Upload the working calculations that show the critical path, including the forward and backward passes.
Question 2: What is the critical time for this project?
A 20 days
B 18 days
C 19 days
D 21 days
Question 3
There will be a two-day penalty based on the critical time calculated. This statement is:
True
False
Question 4
What is the total float of the activity "Windows"?
A 3 days
B 2 days
C 1 day
D Zero float
Question 5
What is the free float of the activity "doors", with the successor activity "door opener"?
1 day
zero days
3 days
2 days
Question 6
After some negotiation with the Simpsons, they have agreed to a new end date. What would the project float be if you had to complete the project in 25 days?
zero days
5 days
7 days
8 days
Question 7
What is the total float of Activity C - "Erect Frame"?
Zero days
2 days
3 days
Question 8
Will you receive a bonus or a penalty at the end based on your original critical time?
Bonus
Penalty
Question 9
What is the early start (ES) of activity J - "Paint"?
Day 15
Day 17
Day 19
Day 16
Question 10
A new resource has been assigned to task G "Electrical". This resource takes one day extra to complete the task. The new duration of the task is 4 days. The critical time:
Remains the same
Has increased by 1 day
Has increased by 2 days
The critical time is now 19 days
Question 11
Use the original information posted for this question.
The task I - "Door Opener" has a specialist working on it. However, a new resource has been assigned and he takes 5 days to complete the task. Based on this change, there are two opinions: the Simpsons and the Project Team. The Simpsons think it will now complete in 22 days, however, the project team thinks it will take 21 days. Who is correct?
The project team
The simpsons
They are both wrong
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books

Students also viewed these General Management questions