table [ [ ID , Activity,Predecessor,Duration ] , [ A , Prepare Site,None, 2 ] , [ B , Pour Foundation,A , 3 ]
tableIDActivity,Predecessor,DurationAPrepare Site,None,BPour Foundation,ACErect Frame,BDRoof,CEWindows,CFDoors,CGElectrical,CHRoughIn Frame,DEFIDoor Opener,F GJPaint,H I,KClean UpThis assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the project below.
You have signed a contract to build a garage for the Simpsons. You will receive a $ bonus for completing the project within days. The contract also contains a penalty clause in which you will lose $ for each day the project takes longer than the agreed days.
Draw a project network given the information below. Then, do the following:
Complete the forward and backward pass
Determine the critical path
Compute the Total slack for all activities
Determine which activities have free float
Then answer the following questions.tableIDActivity,Predecessor,DurationAPrepare Site,None,BPour Foundation,ACErect Frame,BDRoof,CEWindows,CFDoors,CGElectrical,CHRoughIn Frame,DEFIDoor Opener,F GJPaint,H I,KClean Up
Question
Upload the working calculations that show the critical path, including the forward and backward passes.
Question : What is the critical time for this project?
A days
B days
C days
D days
Question
There will be a twoday penalty based on the critical time calculated. This statement is:
True
False
Question
What is the total float of the activity "Windows"?
A days
B days
C day
D Zero float
Question
What is the free float of the activity "doors", with the successor activity "door opener"?
day
zero days
days
days
Question
After some negotiation with the Simpsons, they have agreed to a new end date. What would the project float be if you had to complete the project in days?
zero days
days
days
days
Question
What is the total float of Activity C "Erect Frame"?
Zero days
days
days
Question
Will you receive a bonus or a penalty at the end based on your original critical time?
Bonus
Penalty
Question
What is the early start ES of activity J "Paint"?
Day
Day
Day
Day
Question
A new resource has been assigned to task G "Electrical". This resource takes one day extra to complete the task. The new duration of the task is days. The critical time:
Remains the same
Has increased by day
Has increased by days
The critical time is now days
Question
Use the original information posted for this question.
The task I "Door Opener" has a specialist working on it However, a new resource has been assigned and he takes days to complete the task. Based on this change, there are two opinions: the Simpsons and the Project Team. The Simpsons think it will now complete in days, however, the project team thinks it will take days. Who is correct?
The project team
The simpsons
They are both wrong
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started