Question

1 Approved Answer

table [ [ Job , Job time,Due date ] , [ A , 1 3 , 4 5 ] , [ B , 1

\table[[Job,Job time,Due date],[A,13,45],[B,10,16],[C,7,22],[D,5,17],[E,14,39],[F,17,27],[G,11,19]]
The table contains information concerning the 7 jobs that are arrived and awaiting processing at a work center. Determine the sequence using LPT, EDD & CR. Then compute the Avg. job in the systems and lateness, and utilization. What is your conclusion?