Table Q2: Project Activities Time Estimates (weeks) Activity ID Predecessor Optimistic duration Most likely duration Pessimistic Duration A - 1 4 7 B - 2
Table Q2: Project Activities Time Estimates (weeks)
Activity ID | Predecessor | Optimistic duration | Most likely duration | Pessimistic Duration |
A | - | 1 | 4 | 7 |
B | - | 2 | 6 | 7 |
C | B | 3 | 3 | 6 |
D | A | 6 | 13 | 14 |
E | A,C | 3 | 6 | 12 |
F | B | 6 | 8 | 16 |
G | E,F | 1 | 5 | 6 |
(a)Draw a network diagram (A-o-N) for the project showing ES, EF, LS, LF, and slack for each activity.
(b) Determine the critical path and the project completion time.
(c) What is the probability of completing the project within 23 weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started