Question
Task Description Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time Expected Time Variance A Identify equipment requirements none 4 6 8 8+4(6)+4/6=6 [8-4/6]= .444
Task
Description
Immediate Predecessor
Optimistic Time
Most Likely Time
Pessimistic Time
Expected Time
Variance
A
Identify equipment requirements
none
4
6
8
8+4(6)+4/6=6
[8-4/6]=
.444
B
Solicit bids from vendors
none
6
8
16
16+4(8)+6/6=9
[16-6/6]=
2.777
C
Select a system/vendor
A,B
2
4
6
6+4(4)+2/6=4
[6-2/6]=
.444
D
Place order for system
C
8
10
24
24+4(10)+8/6=12
[24-8/6]=
7.111
E
Redesign warehouse layout
C
7
10
13
13+4(10)+7/6=10
[13-7/6]=
1
F
Implement new warehouse design
E
4
6
8
8+4(6)+4/6=6
[8-4/6]=
.444
G
Design system interface
C
4
6
20
20+4(6)+4/6=8
[20-4/6]=
7.111
H
Integrate the interface into the system
D,F,G
4
6
8
8+4(6)+4/6=6
[8-4/6]=
.444
I
Install the system
D,H
4
6
14
14+4(6)+4/6=7
[14-4/6]=
2.777
J
Train system operators
H
3
4
5
5+4(4)+3/6=4
[5-3/6]=
.111
K
Test system
I,J
2
4
6
6+4(4)+2/6=4
[6-2/6]=
.444
Total variance= 23.111
Task
Normal Cost
Crashed Time
Additional Cost to Crash 1 week ($)
A
1,000
4
450
B
1,000
7
400
C
1,500
2
600
D
2,000
8
300
E
5,000
7
1,000
F
3,000
4
550
G
8,000
5
750
H
5,000
4
700
I
10,000
4
800
J
4,000
3
400
K
5,000
3
500
Based on the information provided, answer the following questions.
B)How many weeks will be required to complete the project based on the normal time?
A-C-D-I-K = 6+4+12+7+4 = 33 weeks
A-C-D-H-J-K = 6+4+12+6+4+4 = 36 weeks
A-C-E-F-I-K = 6+4+10+6+7+4 = 37 weeks
A-C-E-F-H-J-K = 6+4+10+6+6+4+4 = 40 weeks
A-C-G-H-J-K = 6+4+8+6+4+4 = 32 weeks
B-C-D-I-K = 9+4+12+7+4 = 36 weeks
B-C-D-H-J-K = 9+4+12+6+4+4 = 39 weeks
B-C-E-F-I-K = 9+4+10+6+7+4 = 40 weeks
B-C-E-F-H-J-K = 9+4+10+6+6+4+4 = 43 weeks
B-C-G-H-J-K = 9+4+8+6+4+4 = 35 weeks
The project completion time is the maximum duration of paths. Hence, the project completion time is 43 weeks
C)Based on your answer to part a, which activities are on the critical path?
B-C-E-F-H-J-K
D)What is the total cost required for completing this project on normal time?
Total cost = 1000+1000+1500+2000+5000+3000+8000+5000+10000+4000+5000 = $ 45,500
E)What is the probability of completing the project in 40 weeks? Round calculations to at least 4 decimal places.
{ pessimistic time-optimistic time/6}
Standard Deviation = Square root of the total variance = [23.111]= 4.807 weeks
z40-43/4.807=z-.624 is .2633
Therefore, the probability of completing the project in 40 weeks is 0.2633
F) If Kerry Goins wishes to finish the project 2 weeks sooner, which activity(ies) should be crashed and by how much? Those critical path activities must be crashed which have lesser crash cost. Activity B or J can be crashed since both have less crash cost of $ 400 per week.
G) How much will finishing the project 2 weeks sooner increase the total project cost?
$45,000+(6450*2)=$57,900
answer the following 2 questions
H) What is the maximum number of weeks that this project can be crashed?
I) How much would the total cost increase if the project was fully crashed?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started