Task | Immediate Predecessor | Task Length (Days) |
A |
| 2 |
B | A | 3 |
C | B | 1 |
D | B | 4 |
E | C,D | 2 |
What is the critical path?
A-B-D-E
A-C-E-F
B-D-E-F
A-F-G-H
Calculate the expected completion time.
7 days
11 days
19 days
20 days
What is the slack for task C?
1 day
3 days
5 days
7 days