Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Task Predecessors Duration A - 3 weeks B - 4 C A 2 D C 5 E B 7 F D, E 1 G D

Task Predecessors Duration
A - 3 weeks
B - 4
C A 2
D C 5
E B 7
F D, E 1
G D 4
H F, G 5

Draw an AOA (Activity on Arrow) diagram of the project.

Indicate the ES (Earliest Start), EF (Earliest Finish), LS (Latest Start), LF (Latest Finish) times for each of the activities A through H.

Tabulate the slacks of the tasks.

What is the critical path(s)

How many weeks does it take to complete the project according to the critical path analysis?

An activity has three estimates: Optimistic = 10 weeks, Pessimistic = 25 weeks, Most-Likely = 15 weeks. What is the estimate according to the three-point estimation method for this activity? What is the standard deviation for this activity?

A project node has ES=21 weeks, LS=37 weeks, LF=39 weeks. Compute the duration, float (slack), and EF for this node.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Records And Database Management

Authors: Jeffrey R Stewart Ed D, Judith S Greene, Judith A Hickey

4th Edition

0070614741, 9780070614741

More Books

Students also viewed these Databases questions

Question

List some major causes of absenteeism in organisations.

Answered: 1 week ago