Question
Task This is an individual assignment worth 3%. You are required to produce a workforce plan to best achieve the daily production schedule, in the
Task
This is an individual assignment worth 3%. You are required to produce a workforce plan to best achieve the daily production schedule, in the detailed scenario below. The information provided in the DC Design Exercise provides the background of the DCs volumes and operational information. Assume that the DC has implemented a training schedule of cross-training, and all direct workers can be employed in any of the direct areas. Develop a workforce plan to best satisfy the daily workload with the direct labour provided.
Scenario
The date is 5 Feb 2023
The workload for the day has just been announced:24 Containers need to be unloaded
960 pallet Putaways
48 Store shipments deadline for meeting the transportation cut-off is 11.59pm.
9,000 Picks
600 Pallet Replenishments from storage to pick location
500 SKUs require Cycle Counting
Sector Retail
Operating hours 2 shifts, 8 hours a day Mon-Fri, 7.30am 11.30pm. Assume that the workforce is split equally between the 2 shifts.
Staff 170Indirect:
Management - 7
Clerical - 11
Maintenance - 4
Janitorial - 4
Battery Changer - 2
Security - 2
Direct workers:
Receivers 35
Putaway/Replenishment drivers 15
Pickers 30
Shippers - 55
Inventory - 5
Productivity per worker
Pallet Putaway productivity 15 pallets/hour (taking full pallets from receiving area to pallet racks)
Pallet Replenishment productivity 15 pallets/hour (pulling full pallets out of racks onto the floor picking locations)
Picking productivity 30 picks/hour (picking to shipping area for customers)
Inventory Count productivity 15 SKUs/hour
Inbound Receiving 100 floor-loaded containers per week, or 15 person-hours per container. (unloading a container/truck)
Outbound Shipping 200 store shipments per week, or 10 person-hours per shipment. (loading a truck)
Report
Submit the excel file to Brightspace (D2L Workforce Balancing) by the due date. Your excel file submission should show how you have allocated your workers to each area given that you dont have enough workers to get everything done. Identify any shortfalls and explain why your allocation of direct workers is the best option. Tip: Think about the flow through the facility and the importance of the customer.
Sum of Workers Available should equal the sum of the Workers AssignedStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started