Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate Predecessor(s)

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Activity

Time

(in hours)

Immediate Predecessor(s)

A

7.0

B

7.2

C

6.0

A

D

8.0

B, C

E

4.8

B, C

F

8.1

D

G

4.0

E, F

This exercise contains only part a.

a) The correct precedence diagram for the project is shown in

Figure 3

Figure 1

Figure 2

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Activity

Time

(in hours)

Immediate Predecessor(s)

A

7.0

B

7.2

C

6.0

A

D

8.0

B, C

E

4.8

B, C

F

8.1

D

G

4.0

E, F

This exercise contains only part a.

a) What is the correct precedence diagram for the project

..

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Improving Supply Chains In The Oil And Gas Industry

Authors: Sanchay Roy, Stewart Dunbar

1st Edition

3030950654, 978-3030950651

Students also viewed these General Management questions

Question

International conference on population and development ?

Answered: 1 week ago

Question

Approach to population ?

Answered: 1 week ago

Question

The concept of development ?

Answered: 1 week ago

Question

To make available communication media?

Answered: 1 week ago

Question

Explain the treaty of purandar in ancient time ?

Answered: 1 week ago