Question
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate Predecessor(s)
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
Activity | Time (in hours) | Immediate Predecessor(s) |
A | 7.0 | |
B | 7.2 | |
C | 6.0 | A |
D | 8.0 | B, C |
E | 4.8 | B, C |
F | 8.1 | D |
G | 4.0 | E, F |
This exercise contains only part a.
a) The correct precedence diagram for the project is shown in
Figure 3
Figure 1
Figure 2
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
Activity | Time (in hours) | Immediate Predecessor(s) |
A | 7.0 | |
B | 7.2 | |
C | 6.0 | A |
D | 8.0 | B, C |
E | 4.8 | B, C |
F | 8.1 | D |
G | 4.0 | E, F |
This exercise contains only part a.
a) What is the correct precedence diagram for the project
..
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started