Question

1 Approved Answer

Tauch Technologies is considering two potential projects, X and Y. In assessing the projects' risks, the company estimated the beta of each project versus both

Tauch Technologies is considering two potential projects, X and Y. In assessing the projects' risks, the company estimated the beta of each project versus both the company's other assets and the stock market, and it also conducted thorough scenario and simulation analyses. This research produced the following data:

Project XProject YExpected NPV$350,000$350,000Standard deviation (NPV)$150,000$100,000Project beta (vs. market)0.81.4Correlation of the project cash flows with cash flows from currently existing projectsCash flows are not correlated with the cash flows from existing projectsCash flows are highly correlated with the cash flows from existing projects

Explain the type of risk that the projects face. Does one project have more risk than the other?Show your calculations, if any, and explain your answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Business The Challenges Of Globalization

Authors: John J. Wild, Kenneth L. Wild

9th Edition

0134729226, 978-0134729220

More Books

Students also viewed these Finance questions

Question

Critically assessing how are they efficient?

Answered: 1 week ago