Question
Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based
Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:
Machine-hours required to support estimated production | 225,000 | |
Fixed manufacturing overhead cost | $ | 4,275,000 |
Variable manufacturing overhead cost per machine-hour | $ | 2.00 |
Required:
1. Compute the plantwide predetermined overhead rate.
2. During the year, Job P90 was started, completed, and sold to the customer for $3,700. The following information was available with respect to this job:
Direct materials$1,702
Direct labor cost$1,221
Machine-hours used 84
Compute the total manufacturing cost assigned to Job P90.
Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 225,000 $ 4,275,000 2.00 $ Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job P90 was started, completed, and sold to the customer for $3,700. The following information was available with respect to this job: Direct materials Direct labor cost Machine-hours used $ 1,702 $ 1,221 84 Compute the total manufacturing cost assigned to Job P90. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the plantwide predetermined overhead rate. Predetermined overhead rate per MH Complete this question by entering your answers in the tabs below. Required 1 Required 2 During the year, Job P90 was started, completed and sold to the customer for $2,500. Compute the total manufacturing cost assigned to Job P90. Direct materials Direct labor Overhead applied Total manufacturing cost 0Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started